A hypothetical call, and the thought process on the receiving end, from the first question to a documented decision.
"The equipment delivery has slipped. We can expedite an alternate shipment for $25,000, but we need authorization today to protect the schedule."
Interactive call
Investigate what you need, then decide. About three minutes.
Incoming call
Dan, the contractor's project manager
You'll hear Dan's side; your questions are on screen. Every line is captioned.
Dan
Connectingโฆ
What do you want to ask?
0 of 16 askedReady, or out of time? You can decide whenever you like.
Expedite an alternate shipment.
$25,000. Authorization needed today.
A promised delivery improvement still needs to translate into a project completion improvement.
Switch on each cost the quote might not cover, and the site cost you might avoid. The total starts at the contractor's quote.
The quoted price may be only one part of the decision's cost.
Within budget does not automatically mean affordable given the risks still ahead.
| Model area | Ask for each path |
|---|---|
| Construction cost | What is the revised total forecast cost, including secondary effects? |
| Funding | If existing funding is insufficient, where will the additional cash come from? |
| Timing | When must the money be paid, and does that create a cash shortfall? |
| Revenue | Does the revised operating date change when revenue or savings begin? |
| Financing costs | Does a longer construction period change interest, fees or other carrying costs? |
| Returns and obligations | How do the options affect modeled returns, debt metrics and contractual milestones, where applicable? |
Contingency is a budget allowance, not a separate source of cash. Check how it is represented in the model so the same cost is not counted twice.
Approval authority varies by project and contract.
Can the recovery actually be delivered, and on what terms?
What happens to forecast cost, cash requirements and returns?
Does it improve the controlling schedule path?
Who accepts the expenditure and remaining risk?
Does substitution require design changes, compatibility checks or new approvals?
What do the contract and change process require?
What changes in the updated operations schedule, and when does handover now happen?